5.102.6
The person responsible for an electrical installation shall determine and record with
justification:
— the inspections to be carried out,
— the time between two successive inspections,
— the representative random sample,
— the measurement methods that are to be used and
— any measurement instruments that are to be used.
The regulations of the electrical work
5.102.7
Samples are only allowed if:
— low-risk electrical work equipment is concerned that is used under the same conditions
and
— the sum of the weighting factors in
annex K for this electrical work equipment is less than 16.
5.102.8
Electrical work equipment shall be demonstrably approved for use.
NOTE This can be demonstrated by means of a register stating the date of inspection, the
date of the next inspection, the inspection method and the approval. A sticker with
the next inspection date may also be applied to the electrical work equipment.
5.102.9
When inspecting electrical work equipment, it shall be checked whether the requirements
are met relating to:
a) the protection measures against:
— electrical shock;
— thermal effects;
— overcurrent;
— voltage failure;
b) the correct operation of the safety systems;
c) the correct use in view of the environmental conditions.
5.102.14
If the requirement of the insulation resistance cannot be complied with for electrical
work equipment of class I with heating elements, the actual leakage current may be
measured. The leakage current measured must not exceed the value of
table 103.
Table 103
—
Maximum values of the leakage current for class I electrical work equipment with heating
elements
Power
kW
Actual leakage
5.102.16
The resistance R of the protective conductor in connecting cables, extension cords and reels, including
the contact resistances, shall comply with:
where:
R
is the resistance of the protective conductor, including the contact resistances,
in Ω;
ρ
is the specific resistance of the conductor material, in Ω.mm2/m;
l
is the length of the protective conductor, in m;
S
is
6.1.0.101
The person who carries out the work activities shall be nominated for this. Any person
who has not been nominated for carrying out the work activities shall be under the
supervision of a person nominated for this purpose.
If the nominated person in control of a work activity does not actually manage the
work, this task may be delegated to a skilled person. This shall preferably be set
down in
6.2.3.101
The dead state may only be established using double-pole voltage indicators that comply
with or are equivalent to
NEN-EN-IEC 61243-3. The voltage indicators shall be checked for proper operation directly before and
after use.
6.3.0.104
Work in the live working zones of installations with in-line cartridge fuses of 100 A
to 630 A or automatic fuses of 25 A to 80 A requires the use of personal protective
equipment and a face mask.
NOTE The difference between the value of the cartridge fuse and the value of the automatic
fuse is caused by the amount of energy (I2t) transmitted in case of a short-circuit.
6.3.0.105
Safe working in the live working zones of installations with in-line cartridge fuses
of more than 630 A or automatic fuses of more than 80 A is not permitted because of
the arc hazard, unless the possible energy released has been calculated and the personal
protective equipment has been adapted for this.
NOTE The difference between the value of the cartridge fuse and the value of the automatic
Zoeken in de website
52 resultaten
NEN 3140+A2:2018 geeft een andere visie op het inspectiebeleid
We werken alweer drie maanden met NEN 3140+A2:2018. Dit artikel gaat over de gewijzigde benadering van de inspecties van bestaande elektrische installaties. Dit kan een reden zijn voor de installatieverantwoordelijke (IV) zijn inspectiebeleid te herzien.
In 5.3.3.1.101 van NEN 3140+A1: 2015 staat een bepaling die stevig in het gedachtengoed van elektrotechnisch Nederland is verankerd: “Bij inspectie
Inspectiefrequentie installaties
Artikel 5.101 uit NEN 3140 geeft de eisen weer van een inspectie van bestaande elektrische installaties. De tijd tussen twee opeenvolgende inspecties moet voldoen aan bijlage I. Met deze rekentool kunt u bepalen hoeveel tijd er tussen inspecties mag zitten. Een afzonderlijk tijdsinterval kan worden vastgesteld voor elke elektrische installatie en voor elk onderdeel van een elektrische installatie.
Rekentools
Deze rekentools helpen u om vast te stellen:
Inspectie- en instructietermijnen
Met Bijlage E kunt u vaststellen wanneer een VOP, VP, WV of IV opnieuw instructie moet krijgen.
Bijlage I geeft de termijn aan voor inspectie van uw elektrische installaties.
Bijlage K geeft de termijn aan voor inspectie van uw elektrische arbeidsmiddelen.
Steekproefbepaling
Met bijlage J kunt u de grootte
Bestaat er een NEN 3140-keuringssticker?
Nee, die bestaat niet. De eis die in de norm wordt gesteld, is dat elektrische arbeidsmiddelen aantoonbaar moeten zijn goedgekeurd voor het gebruik (bepaling 5.102.84 in de norm). De wijze waarop dit aantoonbaar wordt gemaakt, is niet voorgeschreven.
Moet bij het plaatsen van een cv-ketel worden voldaan aan NEN 3140? In het bijzonder op het onderdeel brandwerende doorvoeren en gasbelemmering.
NEN 3140 richt zich op het veilig werken aan en met elektrische installaties en arbeidsmiddelen. Voor oplevering van nieuwe elektrische installaties en arbeidsmiddelen zijn veel uitgebreidere inspecties noodzakelijk. Niet alleen moet dan naar de veiligheidsaspecten worden gekeken, maar ook moet worden gekeken of de functionele eisen goed zijn ingevuld.
Brandwerende doorvoeren en gasbelemmering behoren
NEN heeft een training voor Vakbekwaam Persoon. Wat zijn de leerdoelen van de cursus?
U leert op hoofdlijnen wat de Arbowet vraagt en wat het Arbobesluit aangeeft. Verder wordt u bekend met de inhoud van de norm NEN 3140. Je leert risico’s en gevaren herkennen (waaronder aanrakingsgevaar en de vlamboog) en je leert in de training wat de positie is van de Vakbekwaam Persoon ten opzichte van andere aanwijzingsniveaus binnen een organisatie. Tot slot leer je hoe je veilig werkt aan een